Thursday, November 23, 2017

OneNote and Project Online - Add Efficiency to your Meeting Minutes and Improve Collaboration


Hi All, 

Recently, I had to help a client use the Notebook which is part of the Project Site by default on any Project Online tenant having at least an Office 365 license. you will know if you have access to that if you see this link in your Project Site:

I would like to share with you a nice way to use the notebook embedded in the Project Site to improve the collaboration and information sharing within your project team.
first things first, when clicking on the Notebook link, OneNote Online will open and you will be able to edit the workbook online. as soon as you do this, everyone who have access to the site can see and collaborate in the notebook

Whilst this is already a great feature, let me tell you how powerful is the integration with the overall office suite. Here is the scenario. As a project manager, you setup a meeting that you would like the minutes to be shared across your team.

the first thing you will have to do is to open your notebook using OneNote 2016. while clicking on the Open in OneNote link, on the above screen, OneNote will automatically open and create a link for you to the notebook in the project site. just click on the below and that will be done automatically.

The notebook then opens in OneNote.

Now jumping in outlook, you can now create a meeting invite and include a link to the notebook clicking on the following link

You will have to select the synchronized notebook


That will include this link in the invite that will allow the users (who have access to the Project Site) to access to the notebook from either their OneNote 2016 or from OneNote online.

From that, the magic happens. a new page is created including your meeting attendees and notes that were in the invite. you can now use either the online or the local version of OneNote to provide update and insert minutes or other information. see below the (almost) simultaneous edition of the notebooks from OneNote 2016 (left) to OneNote Online (right)



Obviously, you can also access and edit the information from your phone

I love this functionality. Do you?

Admin Challenge

I encountered a challenge when setting up a new project site template on the notebook name. Indeed, the notebook name on project site created using the new template will use the template's notebook name (Project Site Template in my case which was the name of the site).
Two solutions from ther
1. Renaming the notebook after it is created. thanks tom for these instructions
2. Rename the Project Site Template notebook with a generic name like NoteBook that will be used in all newly created sites


Share this article :

Monday, November 20, 2017

Configure rollup of timephased reporting data in Project Online

Recently the product group has made some improvements to optimize Project Online performances. I particularly think about the project center updates and the EPT configuration to store the project sites out of the PWA site collection.

The last feature, currently being rolled up, is the ability to configure the rollup level of timephased reporting data, used through ODATA, with PowerBI or Excel.
Here is the Microsoft article:

Basically, you'll find a new entry in your PWA server settings, enterprise data section. You'll be able to choose if you want to rollup timephased data at daily (current), weekly, monthly or at fiscal period level.


A few aspects to have in mind:
Any changes require to republish the projects.
  • For new instance (created after the rollup), NEVER will be checked, meaning that this is one of the first parameter to configure for a new instance using odata reporting. You can keep is like this is you don't need timephased reporting data, it will improve your queue performance.
  • For existing instances, DAILY will be selected, which means that it will have to impact on existing reports.


We strongly advice to first change the parameter on a test environment to check that the reports still work. For example, Ion the dashboard I usually deploy, the capacity reports use a weekly or monthly timescale, so I'll have to readjust them.


Share this article :

Monday, October 23, 2017

New PowerBI Project Online report pack: How to customize it on a non-english tenant?

Project team has just released a new report content pack. I won't go into the details: how to deploy it and plug it on your Project Online tenant. It has already been greatly explained, particularly by Paul Mather, a fellow MVP, in a recent post. Another relevant information: you can get the report pack on GitHub.

My contribution will be on another concern, which is related to my context: I'm located in France and working with international customers. Meaning that I often have French Project Online tenants, but I have to generate reports in English. And this is where the report pack has a weakness: it only works as-is on English tenant. So below is the procedure to deploy it on non-English tenant and customize it. 
Thanks by the way for my fellow colleagues to put me on track.

Once you have changed the data source (your non-English PWA tenant URL) as explained by Paul, it still doesn't work because the queries are looking for the english odata feeds. For example, all queries start with the source of the data:
    Source = OData.Feed(#"PWA Site URL" & "/_api/ProjectData"),
    Projects_table = Source{[Name="Projects",Signature="table"]}[Data],

Thing is: on a French tenant, there is no "Project" feed, but "Projet". You can replicate this discrepancy on any queries, so you just get a bunch of errors. The solution is to add [en-US] to tell PowerBI to take the data source in english:
    Source = OData.Feed(#"PWA Site URL" & "/_api/ProjectData/[en-US]"),
    Projects_table = Source{[Name="Projects",Signature="table"]}[Data],

You can do that by clicking on "edit query", select the queries one by one and click on "Advanced editor".

The second trick I want to share is how to personalize the reports. Obviously, the report pack is generic since it should be applicable for any Project Online instance. But you'll surely create custom fields (tasks, projects, resources). For example, for one of my customer, I added the "Region" custom field for projects. This is a key criteria I want to add in my reports.

For that, stay in the query editor and on the right panel, you should see for each query all the applied steps. Check for the "Removed other columns" step. This step is quite important in terms of performance: it will exclude from the query fields you don't need in the report to optimize the query time of processing. By default, all custom fields will be excluded.

When you click on the gear next to the step, you'll open a dialog box with all the available fields off the query. Then just click of the chosen column (custom fields) you want to include in your dataset.

When you close the query editor and apply the changes, you'll see the new custom fields in the available fields.


Et voilà!

2017-20-23: Note that as far as I noticed, there is a bug in PowerBI App where you cannot schedule a refresh on a dataset with [en-US] in the URL data source. I have a support case opened with Microsoft on that and will kept you informed.

Share this article :

Tuesday, October 10, 2017

Power BI: Chiclet slicer with image

Hi, 
I haven't been playing and blogging with PowerBI since a while. Recently for a new customer, I had to display a filter on a PowerBI report to include/exclude important projects which need to be reviewed at board level. Since my tenant was in French but the report was in English, I had something really not satisfying, displaying TRUE or FALSE in a slicer, not really meaningful. The board wanted to have something more graphical. You would just click on the green check mark to select flagged projects. 

Nice isn't it?

Basically, in MS Project it is not more than having a flag enterprise custom field in a PDP to flag in or out projects, associated with a graphical indicator. In the project center, flagged projects are displayed with check marks.

First, find on Internet (free of rights) icons corresponding to your need. Prefer PNG format so the icon's background will be highlighted when selected. You can store the icons on a shared library on your PWA instance, accessible at least in read-only by all Power BI users.

Then in Power BI Desktop, you have to import a custom visual named Chiclet slicer. I won't go in details on how to do this, it has been blogged many times already: here is the support article you can refer to. Once done, open the query editor, select the data source containing your flag (ProjectData in my case) and create a new conditional column.

You'll be able to enter a name and generate outputs based on condition. In our case, the output will be the image URL for each value of the custom field (TRUE or FALSE), with a "else if" condition.

Once validated without error and back to Power BI desktop, you can select your dataset then your new conditional column. In the "Modeling" tab, under "Data category", select "Image URL".

In your report, add the new chiclet slicer visual and drag:
  • the flag enterprise custom field in the category and values zones,
  • the new URL conditional column in the Image zone.


In the widget format settings, you can specifiy the size or the chiclet and the split of the image (100% in my case so only the image is displayed, not the label).

Et voilà!! Note that you can even do that with the Enterprise Project Type which is a pretty common filter. The challenge is more to find meaningful icons. 

You'll also note the nice graphical rendering using conditional formatting in table and the Gantt custom visual which particularly applies to Project Online context. 



Share this article :

Wednesday, October 4, 2017

Highlight days in a Gantt

As moderator of TECHNET forums about Project Server / Online, I often have interesting questions which push me digging concerns I would never have considered.

One recent question I had was as followed. So back to MS Project basics, this is quite simple and immediate to set up but it can bring visibility to stakeholders whom you're sharing the plan with.
"How could we highlight days on an existing task? For example, customer visit on site, strike, MEP, etc... We don't want to create additional tasks or work, neither to create exceptions."

So before going through the steps, here is the final result you can achieve with a 5-minutes configuration.

Starting with the following 10-days new task:

First concept to understand: the bar styles. If you double click on the Gantt chart, you'll open the following configuration box:

You can see that each type of task (normal, manual, critical, milestone, summary, baseline, etc...) has a specific style which can be customized. You might remember that I wrote a post a while ago about customizing bar style based on custom flags. You can also see that each style has a start and a finish. For standard tasks, it is obviously [start] and [finish], whereas for baseline tasks, this is [baseline start] and [baseline finish]. This allows displaying baseline above the task as shown below. 


You understand that mastering bar styles can be quite useful whenever you fall into Gantt customization. So back to our use case, the principle is to use custom start and finish dates. 

1- You can start with the start1/finish1 but you could use additional custom dates if you want to highlight multiple slots.

2- Then customize bar styles with start and finish dates 1 and 2. Note that the new bar styles have to be created BELOW the standard task style so it will be shown on top. Otherwise it would not be visible.

Here is what you get, clear and simple:

3- You might want to add a label as an explanation for highlighting those days. You can use the text 1 and 2 to enter text, and set those custom fields as text displayed on top or below the bar.

Here is the result:

Leonardo da Vinci used to say: "Simplicity is the ultimate sophistication", what do you think?